Sorry for picture quality and quantity but hey, it was pure Baltic!!! Notice the hardcore which has raised the ground level. The patio should look great.
Steps are getting built in the path between the house and the garage.
Week 20 already!! I can't believe it. Well, much of the work carried out this week was outside. The back steps from the lounge are well underway, the drains are all complete and the foundations for the patio are in place too. It took a while to sort out various levels such the alley and how many steps we would need but fingers crossed, we got it right.
A lot more hardcore also arrived and the 'Soffits' guys put the final touches on the roof.
Indoors the last of the door frames and plasterboard went up although the severe storm on Saturday highlighted the fact that the flashings will need tweaked.
The plasterers actually arrived on Wednesday but preparations were not quite complete. They will try again on Monday 19th. (Watch this space).